Bosch (Shanghai) Headquarters
Engineering Geological Detailed
Investigation Report on Plan-built Site

Ⅰ.Preface
1. General Project Situation

It is planned to build Bosch (Shanghai) Headquarters, which is located in
HongQiao LinKong Economy Park, by Bosch(China) Investigation Co.,Ltd. The
plan-built site is near Xiehe Rd. in west, near linhong Rd. in north,near Fuquan Rd. in
east and near Zhujia River in south, The headquarters is 9 floors on ground and 2 floors
in underground,The total building area is 77000m
2
,of which the area of overground is
51000m
2
,the area of underground is 26000m
2
.

The project should be designed by
Suzhou Industry Park Design & Research Institute Co.,Ltd., The investigation area is
about 14,500 m
2
. We are consigned to investigate this built site.
Character of Plan-building and Main Specification
According to design scheme, The project is planed to use pile foundation, and the
concrete

design requirement is as follows: Table 1.
The Character of Plan- building
table1
Data of foundation
Max load
Building Structure
Calculation
column of per
Basement or other fixing allowable
name type
floor type of
Buried
foundation
type depth
spacing column
foundation(area、size、settlement
(m)

depth) (cm)
Head- Frame shear
-9.0 8.4m
2 floors
According
quarters wall
9
Class b pile ×8.4m 13000KN
basement
to code
remark
The 2 gatehouses is planed to use shallow foundation(strip foundation).
According to chapter 3.1 of National standard Code for investigation of geotechnical
1
engineering (GB50021-2001), the importance rank of this project is first, site rank
second, foundation rank second and geotechnical engineering investigation rank second,
so that the investigation rank is class A.
of Investigation, Main Technical Criterions and Code

The main technical standards used in the investigation of this project are as the
follows:
(1)National standard Code for investigation of geotechnical engineering
(GB50021-2001)
(2) National standard Code for design of building foundation (GB50007-2002)
(3) National standard Code for seismic design of buildings (GB50011-2001)
(4) National standard Soil Engineering test Method Standard (GBT50123-1999)
(5) National standard Code for Survey of engineering (GB50026-93)
(6)National standard Enforceability clause for engineering construction
(structural architecture part for 2002 edition)
(7) Industrial standard Rule for multistory building investigation of geotechnical
engineering(JGJ72-2004)
(8) Industrial standard Technical Code for building Pile Foundations(JGJ94-94)
(9) Industrial standard Technical specification for electrical cone penetration test
(CECS 04: 88)
(10) Shanghai project construction specification Code for investigation of
geotechnical engineering (DGJ08-37-2002)
(11) Shanghai project construction specification Code for design of building
foundation (DGJ08-11-1999)
(12) Shanghai project construction specification Code for design of excavation
engineering(DGJ08-61-97)



(13) Shanghai project construction specification Code for seismic design of
buildings (DGJ08-9-2003)
(14) Shanghai project construction specification Code for Geotechnical
Engineering Investigation Document Authorized Depth (DGJ08-72-98)
(15) Shanghai project construction specification Technical code for Ground
Treatment of buildings (DGJ08-40-94)
(16) Shanghai project construction specification Site operating specification for
investigation of geotechnical engineering (DGTJ08-1001-2004)
According to the above code and the technical request put forward by the employer
and designer, some relative specifications and the features of this project, the aim of this
investigation is to investigate the geotechnical engineering condition detailed, carry out
general analysis and appraisal and offer the geological base for the foundation design.
The main engineering geological problems needing resolve are detailed as the
following:
(1)Finding out the character of each stratum, imbed condition and changed
situation within the scope of the investigation depth (65.00m) in the site. Offering
foundation soil physical and mechanical character index of each layer and in-situ
measurement result.
(2)offering the design value and eigen value of the bearing capacity on the nature
foundation; offering the ultimate bearing resistance typical values and verticality
bearing resistance design value ,eigenvalue of individual pile and providing uplift
bearing resistance of uplift pile.
(3)Appraising imbed condition
,
distribution and trait of infection depth for
foundation ditch’s

timbering, and offering parameter for timbering design and
construction.

(4)Appraising the feasibility of pile’s construction and the infection to

surrounding
environment. putting forward prevention and treatment ways.
(5)Making certain the earthquake basic intensity and the site sort. Finding the
liquefaction possibility of saturated sandy silt or sand within the depth scope of 20.0m
in the planned site.
(6)Finding the embed situation and classification of groundwater and in the site
and judging whether it is to corrupt the concrete and subsoil or not;
(7)Finding whether there is any poor geological phenomenon, such as hidden
creek, hidden pond and underground barriers, finding out their distribution range, depth
and characteristic of backfill.
(8)Appraising and analyzing the stability and feasibility of the plan-built site.
,Method of Investigation and Completed Workload
(1)Layout of workload
According to Code for investigation of geotechnical engineering,the

prospect
holes are laid like cancellate in this project, and the boreholes are alternated with CPT

holes,the space of the prospect holes is less than 35.0m or 35m,The little holes are laid
around the foundation ditch,and the space is from 10.0m to 15.0m.
(2)

Method of Investigation
In this investigation, borehole sample, standard penetration test [SPT], cone
penetration test [CPT],

vane shear test,

injection test and laboratory soil test are used.
(2.1).Boring:using borer(type H-30)with silt slurry encasing to headway, and
according to the subsoil’s character, picking off soil samples with

pistontype open
sample quality scale of samples isⅠtoⅡ.
(2.2).SPT:using drop hammer(63.5Kg) to test, and the drop height is 76cm. Test
point space is 2.0~3.0m, The SPT is carried though in silt and sand under

2


blow count of every point should be noted , and the Particle analysis of disturbed soil
samples is necessary.
(2.3).CPT:It is finished with static sounding instrument (type: SYW-15).The probe is
single-bridge with 15cm
2
(probe no. 3803,calibration factor:2.8798KPa).It can reflect
soil’s change in diverse depth. And the CPT data is collected with instrument (type:
LMC-310).
(2.4).Vane shear test:It is finished with electromotive vane shear instrument (type:
ZCB-50).The vane

standard is 50cm×100cm,No.983,calibration factor: 0.01157N.m,
testing space is 1m ,And the data is collected with instrument (type: LMC-310).。
(2.5).Injection test:Insulating non-test with sleeve, observing water level’s dropping
in different time after injection, So that the permeability of associated stratum can be
measured, and the observation time is 2 to 8 hours.
(2.6).Artesian water level observation:using steel tube(diameter: 50mm) to survey
the depth of Artesian water in stratum of ⑤2-1.
(2.7).Little hole:being finished by manpower helical auger, and each footage is no
more than 0.5m.
(2.8).Soil or water test in doors:routine test to undisturbed soil and disturbed soil,and
the special test such as CU, K
0
,K,Qu are necessary to soil within the depth scope of
test of UU is finished in layer ⑧1 because underside of the pile tip is soft
clay.2 sets water samples are adopted in borehole G3 and G10.
ted Workload
This field work was carried out from 21th, August, 2007 and ended on first,
September. The position of prospect holes are measured through its relatively

relative
position with landform and landmark, Surveying every hole’s elevation after field work
test is finished on 31th, August, 2007, and water partial analysis is finished

on 28th, August, workload is as follows:table2

Prospecting Workload
Table2
Item

Workload

Item

Workload

Borehole
65.30m(1),65.00m(5),50.30m(1),
50.00m(3),total footage 590.60m.
W,γ,G 232
CPT
65.00m(4),50.10m(2),50.00m(12),
total footage 960.20m..
Wp , W
L
178
flash hole 23.00m(3),total footage69.0m.. C, Φ 124
vane test 23.00m(3), total footage69.0m..
labor
a, E 163
Field
Little hole 4.00m(41), total footage 164.0m.
atory
Particle analysis 175
work
SPT time
65
soil
unconfined compressive strength 13
undisturbed soil
232
test
K
0
13
disturbed soil
65
CU’ 12
Water sampling
2 sets
UU’ 3
survey
75
KvKh 1718


Water partial analysis 2
5. Elevation System and Basis of Elevation Measurement
In this investigation, the elevations of prospecting points are measured by the
Bench Mark (No.4-116) of Shanghai, which is 4.116m in Wusong elevation
system(2006). It is located at No.6,Zhangjiang ferry, xinjing town,Changning zone.

Ⅱ Geotechnical Engineering Condition of Planned Site

1.
Terrain and Geomorphology

This site is located at the south-east inlet of Changjiang Delta, its geomorphology
is

littoral plain. The hypsography is mostly flat. The borehole elevation of measured
points is within the range from 3.35m to 4.16m, and differential elevation is 0.81m.
During investigation, the removal staff is cleaning up the old foundation,so the part of
the plat isn’t level up,and its elevation only 2.51m.
3


2.
Compositions and Character of Foundation Soil

In this investigation, maximum prospecting depth is 65.3m, and within the scope,
the found foundation soil belongs to the Quaternary deposit, which is composed of silty
soil,clay soil and sandy soil. According to their structural character, properties and
difference of physical and mechanical character, the foundation soil can be divided into
7 layers, see attached table character of every stratum can be seen in Stratum
Speciality Table and Borehole Log.

Composition of foundation soil
table3
Stratum
No.
Stratum Name geologic age
genetic type distributing
①1 Filled soil Q
3
4
Filled soil all over

Brown yellow
~grey yellow silty clay
Q
3
4
Coastal~bayou
all over,
thin in old foundation
③ Grey mucky silty clay Q
2
4
Coastal~shallow sea all over
④ Grey mucky clay Q
2
4
Coastal~shallow sea all over
⑤1 Grey mucky silty clay Q
1
4
Coastal, morass all over
⑤2-1 Grey clay silt Q
1
4
Coastal, morass all over
⑤2-2 Grey silty clay Q
1
4
Coastal ,morass all over
⑤2-3 Grey clay silt Q
1
4
Coastal, morass all over
⑤3 Grey brown silty clay Q
1
4
liman all over
⑤4 Grey green silty clay Q
1
4
liman all over
⑦ Grey green~grey silty sand Q
2
3
bayou~Coastal all over
⑧1 Grey silty clay Q
2
3
Coastal~shallow sea all over
⑧2
Grey silty clay interbed silty
sand
Q
2
3
Coastal~shallow sea No penetrated

3. Physical and Mechanical Properties of Foundation Soil
(1) Physical and Mechanical Properties of Foundation Soil Index
In this investigation, we have deleted some abnormal values of the physical and
mechanical of each layer. See Stratum Physical and Mechanical Properties Parameters

(attached No.2-1), and the explanations are as follows:
(1.1)The indexes showed in the table are the maximum, minimum, arithmetic
the design is in under, statistical parameters should be taken into
consideration according to the safe principle.
(1.2)In the table, friction angle Φ of the foundation soil and cohesion c are peak
shear resistance indexes.
(1.3)In the table, static penetration Ps is mini-mean value.
(1.4)In the table,the bow count of SPT is measured value.
(2) Foundation Bearing Value
The foundation bearing eigenvalue is ensured according to Item 5.2.3 in national
standard Code for design of building foundation (GB50007-2002) and Item 13.3.4 in
Shanghai project construction standard Code for investigation of geotechnical
engineering (DGJ08-37-2002). The design foundation bearing value is calculated
according to Item 4.2.3 and Item 4.2.4 in Shanghai project construction standard Code
for design of building foundation (DGJ08-11-1999), combined with CPT,SPT and
investigation experience. The assumed condition for design bearing value calculation is:
strip foundation is 1.50m wide and 1.00m embedded, free water elevation is 0.50m
embedded, the design values (f
d
) and eigenvalue (f
ak
) of foundation bearing capacity of
each layer is in detailed in the table 4.
Foundation bearing design value (f
d
)

eigenvalue(f
ak
) table 4

Stratum
No.
Stratum Name
Ps

C , φ(peak)
f
d
f
ak

(MPa)
C(kPa) φ(°)
(Kpa) (Kpa)

Brown yellow~grey yellow silty clay
0.65 19 21.0
95 75

Grey mucky silty clay
0.59 9 23.0
75 60

Grey mucky clay
0.56 11 16.5
70
55
⑤1
Grey mucky silty clay
1.00 14 20.5
90 70
In the above table, value of f
d
f
ak
is only used for appraising the character of stratum and comparing the soil properties. When the design
is in under, it is calculated on the basis of actual foundation type, size and embedded depth and considered the strength and deformation of
the under- foundation.
4



water
(1) Phreatic
The groundwater in the planned site is phreatic water. The elevation of
groundwater is controlled by precipitation and evaporation, and is related with the
Zhujia rivers nearby. During the investigation, actual embedded depth of the static water
table is ranged from 1.40m to 2.10m, and the correspond water elevation from 1.95m to
2.43m. According to Shanghai project construction specification Code for investigation
of geotechnical engineering, the depth of groundwater table in Shanghai ranges from
0.50m to 0.70m perennial, meanwhile low groundwater table may reach 1.50m. High
groundwater table (0.50m) can be used in calculating bearing capacity of natural base
and checking computations for antifloatage,and low groundwater table(1.50m) can be
used in designing pile and calculating subsicence.
(2)

artesian water
In this investigation,we gauge the depth of micro artesian water head in layer ⑤
2-1 by injection hole(Z1).and know the depth of artesian water head in layer ⑤2-1 is
6.38m, the corresponded elevation is -ng to Item 3.2.1 in Shanghai project
construction standard Code for design of building foundation (DGJ08-11-1999),the
micro artesian water head and artesian water head are below phreatic water elevation in
Shanghai,and the change of water elevation is in cycle,the depth ranges from 3.0m to
designer can take water elevation in

disadvantage.
(3) Corrosiveness of groundwater
In order to distinguish corrosiveness of groundwater, 2 sets of the groundwater
samples are taken from borehole G3, G10. According to the results of analysis
(attached No.15-1) ,the groundwater in this planned site is freshwater. According to the
Shanghai specification code for investigation of geotechnical engineering, groundwater,

and subsoil in this site have no corrosion to concrete, but slight corrosion to steel
structure.

5
Adverse Geologic Phenomenon

According to the result of this investigation, the site wasn’t found any poor
geological phenomenon, such as hidden creek, hidden pond. Because the old foundation
be removing ,the depth of some part of the filled soil is 3.00m.
According to information be provided by owner,combining with excavating the old
foundation,we know that the former Second feedstuff workshop of Shanghai Xinfeng
Feedstuff Factory lied in the site. There are some old base slab and pile,and they
should infect the coming construction,So that attention to designer and construction is
necessary. It can be seen the corrective data attach to

plan layout and pile layout about
Second feedstuff workshop of Shanghai Xinfeng Feedstuff Factory.
6.
Site Earthquake Effects

(1).Basis condition of
site seismic
design
According to national standard Construction antiseismic design standard
(GB50011-2001)and Shanghai project construction specification Code for seismic
design of buildings (DGJ08-9-2003), this site belongs to Ⅳ site, Antiseismic design
intensity of the region is Grade 7. Design basic earthquake acceleration of ground
motion is 0.01g and design earthquake grouping is No.1.

Sedimentary veneer depth is
more than 80m,and equivalence transversal wave is less than 140ms.
(2)Liquefaction distinguish
The investigation result shows that there isn’t some bedded sandy silt and sand
within 20m. The planned site isn’t liquefaction even if antiseismic design intensity of
5


this project is Grade 7.
(3)Antiseismic section divide
According to item 4.4.1 of national standard Construction antiseismic design
standard(GB50011-2001),Most of the shallow layers is soft soil ,and the site is
disadvantage antiseismic section.

Ⅲ. Analysis and Appraisal of Geotechnical Engineering

1. Stability and Feasibility of Planned Site

There is no liquefacient soil layer, no active rupture, no landslide and so on. This
site is stable and suit for construction.
2. Natural Foundation

The investigation result shows that the layer① is too soft and not to be bearing
course of natural foundation. The layer②, its compressibility from medium to high,
water content is 33.1%,void ratio is 0.95,and the mean value PS is 0.65MPa,The soil is
relatively better. it can be chosen for bearing course of natural foundation to light
accessory planed building. The foundation bottom elevation should be 1.50m. When
Layer ② is used as natural foundation bearing course, the design valueeigenvalue is
95kPa75kPa. Designer should calculate bearing capacity according to

practical situation
and confirm foundation buried depth with the depth of filled soil.

Foundation

(1)Chosen for pile foundation bearing course
According to the requirement of designer, the project will be planed to chose pile
soil above of the layer⑤1 in the site is mostly made of soft clay with
low strength and high compressibility,So these soils aren’t chosen for pile foundation
bearing course.

The earthiness of Grey clay silt in Layer⑤2-1 is relatively better with mean value
PS (3.58MPa),The layer buried too shallow in the chose it for pile
foundation bearing course,the pile can’t meet the requirement of design (for short pile
and small individual pile bearing value). So the layer isn’t chosen for pile foundation
bearing course also.
The thickness of Clay in layer⑤2-2,⑤3,⑤4 is too thin and bedded plane

fluctuation is too big, So these layers aren’t chosen for pile foundation bearing course
also.
The earthiness of grey clay silt in Layer⑤2-3 is relatively better ,and its mean
thickness 6.49m,water content 31.6%,void ratio 0.94,compression index 0.24 MPa
-1
and
medium dense. The layer is distributed all over the site, And the layer top elevation is
from-26.80 to -29.53m, So the layer can be chosen for pile foundation bearing course.
With high strength ,grey green~grey silty sand in layer⑦ is distributed all over
the site,and its mean value PS 11.96MPa,mean thickness 4.95m,water content
22.4%,void ratio 0.70,compression index 0.14 MPa
-1
and with medium to low dense.
And the layer top elevation is from -38.50 to - the higher individual pile
bearing value is required , we can choose the layer for pile foundation bearing course.
The layer⑧1 and ⑧2 is mainly compact layer of pile foundation bearing course.
(2)Chosen for pile type and pile size
When choosing layer ⑤2-3 for pile foundation bearing course, according to

pile
engineering geologic condition and circumstance, we can use premoulded pile with
good bearing effect , easy to control quality of construction and quickly progress. The
pile’s sectional area should be from 350×350mm to 400×400mm or Φ
400mm(PHC),We also can use bored pile withΦ choose layer⑦ for pile
foundation bearing course,because layer ⑤2-1 and ⑤2-3 having high strength, We
6


need use PHC with Φ500mm,or bored pile withΦ750mm to Φ800mm.
(3)Evaluation for individual pile vertical bearing value.
According to table6.2.4-1 in Shanghai project construction standard Code for
design of building foundation (DGJ08-11-1999),combined with CPT and investigation
experience, The f
s
and f
p
of premoulded pile, bored pile is ensured. see attached table 5:
Value of f
s
and f
p
table5
Stratum No. Stratum Name
PS
premoulded pile

bored pile
(Mpa) fs(kpa) fp(kpa) fs(kpa) fp(kpa)

Brown yellow
~grey yellow silty clay
0.65 15
15

Grey mucky silty clay
0.59
15(6m up)
20(6m down)

15(6m up)
16(6m down)

Grey mucky clay
0.56 25 20
⑤1
Grey mucky silty clay
1.00 40 30
⑤2-1
Grey clay silt
3.58 50 40
⑤2-2
Grey silty clay
1.97 60 45
⑤2-3
Grey clay silt
5.23 65 2500 50 900
⑤3
Grey brown silty clay
1.70 60 45
⑤4
Grey green silty clay
2.15 65 50

Grey green~grey silty sand
11.96 95 5000 75 1700
Remark: in the table,fs2=q
sia
,fp2= q
pa
.
According to the value of f
s
and f
p
in the above table, assuming that leveling elevation
of the site is 4.00m,The individual pile vertical bearing value of diverse piles are
calculated according to table6.2.4-1 in Shanghai project construction standard Code for
design of building foundation (DGJ08-11-1999), example for hole C11,
attached table 6:






Estimation of individual pile vertical bearing value table6
Base bottom
diameter
bearing course
Calcul-
Depth of pile
Planned
Leveling or
elevation
depth
Pile cated
entering into
Pile
Pile
R
building
Elev.
side
Stratum
(m)
type Hole
bearing
tip
Elev.
length
K
R
d
R
a
(kN
(kN) (kN)
(m) (m)
length
Stratum
(mm)
No.
Name
No.
course (m)
)
(m)
(m)
Square 350×350 1750 1090 875
Pile 400×400
Grey clay
PHC φ400
⑤2-3
silt

C11 1.47 -31.00 26.00
2050 1280 1025
1610 1005 805
Head-
quarters
4.00 9.00 -5.00
Bored pile φ600 1760 1100 880
PHC φ500
Grey
3615 2255 1808
φ750
green~
Bored pile

grey silty
G4 0.85 -41.00 36.00
3810 2380 1905
φ800
sand
4115 2575 2058
remark:the individual pile vertical bearing value in
the above table don’t consider of pile stem strength.

The individual pile vertical bearing value in the above table is calculated with
assuming condition. After the pile design scheme is assured, in order to provide the last
individual pile vertical bearing value ,the designer can calculate individual pile bearing
value according to
Value of f
s
and f
p
(table5)
in this report and carry out individual pile
vertical bearing static load test.
(4)

Recommended value of Es
When calculating pile foundation’s ultimate subsidence, Es under pile tip is adopted
from dead weight to dead weight+additional pressure. According to Stratum
Compression Curve Figure(12-1~12-2), CPT ,blow count,and consider of construction
experience in Shanghai, Recommended value of Es is offered. see attached table 7:

Es under pile tip
table7
Stratum
γ。
Ps N
Soil test Recommended
No.
Stratum Name
(kNm
3
) (MPa) (blow count )
Es Es
(MPa) (MPa)
⑤2-3
Grey clay silt
17.9 5.23 14.5 20 20
⑤3
Grey brown silty clay
18.3 1.70 12 12
⑤4
Grey green silty clay
19.8 2.15 18 18

Grey green~grey silty sand
19.0 11.96 37.1 40 46
⑧1
Grey silty clay
17.7 1.97 12 12
⑧2
Grey silty clay interbed silty sand
18.5 3.21 14 14
7


pile
According the design requirement,some part of the 2 floor basement has no building
on top,and its weight less than buoyance of order to get over
buoyance,the uplift pile is pile tip can be embedding into layer⑤2-3,
pile type and pile size can see attached table 9:
According to table6.2.7 in Shanghai project construction standard Code for design
of building foundation (DGJ08-11-1999) and value of f
s
offered in table5, individual pile
vertical uplift bearing value is calculated, see attached table 9:
Estimation of individual pile vertical uplift bearing value table9

Pile apex face Layer of pile tip
Depth of
diameter Calcul- pile
Planned
Leveling Pile
building
Elevation
depth
or cated entering
Pile tip
length
R′
(m)

Elev.
Pile type
(m)
(KN)
d
(m)
(m)
side length
Stratum
Stratum
(mm)
No.
Name
Hole into layer of
Elev.
No. pile tip
(m)
(m)
Square
350×350
basement 4.00 9.00 -5.00
Pile
400×400 ⑤2-3
Grey
580
Bored pile φ600
clay silt

C11 1.47 -31.00 26.00 670
660
remark: the design value calculating by soil is exceed to the pile stem strength, the pile stem strength is
availability.
2. To clay and silt , uplift bearing coefficient :λ=0.6.
3.

To individual pile vertical uplift bearing,the static load test is feasible

5.

Timbering of

foundation ditch
The project has 2 floor basement, and the ditch has big area and depth(the depth is
9.00m,belong to second grade ditch),so that timbering is necessary. bored pile can be
used acting as earth-supported structure and deep mixing pile,and the function is
seepage proof curtain. The SMW also can be used in er, horizontal
bracing must be set up in ditch, The ways can assure safety of ditch construction.
In order to offer counting parameter for ditch timbering and drainage design, Ccu,
Φcu K
0
,K,qu, vane shear test and injection test in infection depth for foundation ditch’s


timbering are offered in the investigation. see attached table 10:
Parameter for timbering of foundation ditch table10

Indoors test injection
unconfined
Recomme
compressive strength
CU’
Vane
test
No. Stratum Name
Kv Kh
K
nded


Peak
Cmsec
K
qu q′u
K
Ccu φcu Cˊ φˊ KPa
Cms Cms

Cmsec
KPa KPa
St
KPa º KPa º

Brown yellow
② ~grey yellow silty 3.90E-07 5.17E-06 3.28E-06 3.00E-06 88 58 1.6 0.47 26 14.7 8 27.3 33.7
clay

Grey mucky silty
clay
2.82E-07 3.46E-06 3.84E-06 4.00E-06 37 0.48 4 15.0 1 24.7 28.5

Grey mucky clay
2.63E-07 4.96E-06 7.66E-07 4.00E-07 43 0.53 8 12.3 4 22.0 31.5
⑤1
Grey mucky silty
clay
2.33E-07 2.82E-06 1.56E-06 3.00E-06 62 30 2.3 0.51 19 12.7 5 23.0 17.6
These factors should be considered in ditch timbering design:

(1). The depth of the skirt pipe should be ensured through contract in technology
and economy,

checking calculation of the items such as stability,deform, anti
capsize,anti gliding for ditch bottom soil.

(2).Considering the connection between ditch timbering and surrounding building.
ensuring surrounding building g deep well point or ejection well point for
hydrometeor before ditch excavation, making groundwater under ditch bottom to 0.5

1.0m. filly considering infection of precipitation to surrounding.

(3).In the scope of ditch,there are layer

,

and

,and the ditch bottom lies on
the bottom of layer

.because layer

is loose, easy to collapse, and layer

is soft
clay, having the clear character of thixotropy and rheologic,the strength of layer

is
very easy to reduce by momentum effect,So that when excavating,we must reduce soil’s
disturb as e of the depth of ditch, soil in bottom of the ditch will be
some rebound, paying attention to disadvantage infection to timbering,nearly built
building, underground line and pile rip.

(4).There are micro artesian water in layer
⑤2-1、⑤2-
3 and artesian water in
8


layer

and respectively layer top depth of layer

2-1,

2-3 and layer

is no less
than24.40m,30.30m and 42.00m

according to item 13.3.3 in Shanghai project
construction standard
Code for investigation of geotechnical engineering

(DGJ08-37-2002).considering disadvantage factor, adapting artesian head to
3.0m,Through calculating,layer

2-1 PczPwy=1.29

1.05,layer

2-3 PczPwy=1.40

1.05

layer

PczPwy=1.52

1.05

So that micro artesian water in layer

2 and
artesian water in layer

don’t occur boiling of sand to ditch bottom.
(5).The ditch excavation is too big, the way of symmetry excavation and fitting
supporting in zoning is g 200

300mm thickness earthwork for leveling up
by man power, and laying blanket at the first time. preventing bottom soil to be
disturbed.
(6).Ditch bottom don’t discover for a long time when excavating,say nothing of
ponding, checking calculation anti buoyance when hydrometeor is stopped.
(7).Strengthening deformation inspection to ditch timbering system and out of the
system, ensuring surrounding building safety and the construction going on wheels.

In a word,ditch timbering and earth excavation is emphases and difficulty in the
project. In order to ensure ditch construction safety,

construction design should be
compile carefulness before construction.
feasibility of pile’s construction and the infection to surrounding
environment
Because of old foundation, whatever adopting premoulded pile or bored pile ,it is
necessary to deal with old foundation, and keep away from the position of old
foundation.
The planed site is 17.0m away from Zhujia river in south, 18.00~26.00m away
from Xiehe road in west, 42.0m away from apartment in the project use

premoulded pile, properly measure should be taken,such as: rational circulation,
controlling sinking speed, digging channel for anti pressing,setting stress release hole
near the built building ,road,and underground utilities,So that reducing or avoiding
infection of disadvantage to surrounding building and underground utilities. and doing
inspection layer⑤2-3 being chosen for pile foundation bearing course,pile stem
should penetrate layer⑤2-1 with higher strength and enter into layer⑤2-3 certain depth
So the resistance is big. If layer ⑦ being chosen for bearing course ,pile stem should
still penetrate layer⑤2-3, ⑤3 and ⑤4,and the resistance is bigger. So that in this
project PHC is appropriate, and before construction, in order to choose appropriate
hammer weight, pile cushion,pile strength etc. pile sinkage testing is the
sinkage is difficult,bored pile can be chosen.
When adopting bored pile ,finished pile is easy, But should be attention to quality
control,assuring finishing hole,clearing hole and impregnate quality,and blowdown in
site.
Ⅳ.
Conclusions and Suggestions

(1). This site is stable and suit for construction.
(2). The layer ② i.e. brown yellow~grey yellow silty clay is relatively better, So
that it can be choosen for bearing course of natural foundation to light accessory planed
foundation bottom elevation should be 1.50m. When Layer ② is used as
natural foundation bearing course, the design valueeigenvalue is er
should calculate bearing capacity according to

practical situation and confirm
foundation buried depth with the depth of filled soil.
(3) According to the result of this investigation, the site wasn’t found any poor
geological phenomenon, such as hidden creek, hidden pond. Because of old foundation,
it is necessary to deal with old foundation, and keep away from the position of old
9


foundation.
(4)According loading and foundation soil,We advice adopting layer⑤2-3 for
bearing necessary,layer⑦ can be chose as bearing pile type,pile
length and pile size can see attached the pile design scheme is assured, in
order to provide the last individual pile vertical bearing value ,the designer can calculate
individual pile bearing value according to
Value of f
s
and f
p
(table5)
in this report and carry
out individual pile vertical bearing static load test.
(5) According the design,some part of the 2 floor basement has no building on
top,and its weight is less than buoyance of order to get over
buoyance,the uplift pile is pile tip can be embedding into layer⑤2-3, pile
type and pile size can see attached table 9, To individual pile vertical uplift bearing, the
static load test is feasible.
(6) During the investigation, actual embedded depth of the static water table is
ranged from 1.40m to 2.10m, High groundwater table (0.50m) can be used in
calculating bearing capacity of natural base and checking computations for
antifloatage,and low groundwater table(1.50m) can be used in designing pile and
calculating subsicence.
In this investigation,we gauge the depth of micro artesian water head in layer

2-1 is 6.38m, ccording to Item 3.2.1 in Shanghai project construction standard
Code for
design of building foundation
(DGJ08-11-1999),the micro artesian water head and
artesian water head are below phreatic water elevation in Shanghai,and the change of
water elevation is in cycle,the depth ranges from 3.0m to 11.0m. Through calculating,
the artesian don’t occur boiling of sand to ditch bottom.
According to the results of analysis ,The groundwater and subsoil in this site have
no corrosion to concrete, but slight corrosion to steel structure.

(7) this site belongs to Ⅳ site, Antiseismic design intensity of the region is
Grade 7. Design basic earthquake acceleration of ground motion is 0.01g and design
earthquake grouping is No.1. The investigation result shows that there isn’t some
bedded sandy silt and sand within 20m. The planned site isn’t liquefaction even if
antiseismic design intensity of this project is Grade 7.
(8) The project has 2 floor basement, and the ditch has big area and depth(the
depth is 9.00m,belong to second grade ditch),so that timbering is necessary. bored pile
can be used acting as earth-supported structure and deep mixing pile,and the function is
seepage proof curtain. The SMW also can be used in er, horizontal
bracing must be set up in ditch, The ways can assure safety of ditch construction.
Relatively parameter be attached to table 10.
(9) When adopting premoulded pile, the resistance is big, So that PHC and pile
sinking facility with high-power can be used. Because the building around the plan site
are in scope of crush soil effect, prevention measure is necessary. In order to reduce
noise, static pressure is preferred.
When adopting bored pile, should be attention to quality control, assuring finishing
hole, clearing hole and impregnate quality, and blow down in site.